PROJECT MANAGEMENT
Our big knock down rebuild, this job was premium from start to finish. We kicked off the planning and design phase for this project in July 2019 and it was an 18-month all in labour of love (with the construction phase taking 13-months).
After many months of planning and liaising with council on designs and approvals, onsite construction started in November 2019 and wrapped up in December 2020.
The approval process consisted of pre-DA, DA and a 4.55 modification with many challenges with council along the way!
Our custom electrical plans for this job were like no other. With multiple suspended concrete slabs, we needed to map out and rough in the electrics for the kitchen, dining and living area before the slab above was poured, due to a ‘strip finish’ concrete ceiling. This resulted in hours on site precisely measuring out every downlight, pendent light, strip light and general power location.
Inner city terrace living also meant ensuring neighbours on either side needed to be kept informed and maintain good working relationships with them as they were going to be impacted by the build.
INTERIOR DESIGN
Design Brief: A contemporary industrial home with an impactful street presence, whilst sitting quietly amongst its neighbours.
Scope: Full design including all technical drawings and finishes selections for:
Flooring selection – polished concrete finish, herringbone engineered flooring
Paint palette - internal & external
Internal door, skirting, architrave profiles
Front door profile and finish
Door furniture and cabinetry hardware
Light fittings in stairwell, kitchen, living, master ensuite, powder room, exterior
Exterior tiling and paving
Kitchen
Butler’s pantry
Laundry
Powder room
Guest ensuite
Master walk in robe
Master ensuite
Family bathroom
Bedroom built in robes x2
BUILD
Knock down & re-build of a 5 split level terrace
Extensive underpinning for both neighbouring properties
Heated polished concrete floor & strip finish ceiling on sub ground level
Build consisted of three concrete slabs, 2 of which are suspended
Shadow-line ceiling detailing throughout
Sub-ground rain water tank and drainage cell
Reclaimed brick exterior
Sub-ground floor constructed using a Dincel wall system
New double carport & driveway layback
Trade management of electrical, plumbing, plastering, tiling, painting, bricklaying, aircon, roofers & engineers.